Install time for government electric is about 1 month and the cost is about 40,000b. 28,000b for the cable, and 12,000b for the install.
I have my cables installed and I am willing to let someone use my power lines until theirs are installed. My neighbors let me do the same while I was building.
We currently use very old wooden poles which are now becoming overcrowded. We have plans to put in concrete poles in 2008. They should cost under 8000b per resident.